the township engineers to map out the district.
4. Property owner will pick up
petition and get necessary signatures.
5. Property owners submit necessary
signatures on petition to Assessing Department (whomever is on Property Deed
must sign).
6. Assessing Department will
verify signatures to ensure that the minimum 51% of the property owners have
signed the petition.
7. If the 51% of the property
owners have signed the petition, it will then go to the Township Board for the
first meeting (Intention to Undertake Project).
8. Engineers will go out for bids
for the project to determine the cost of the project.
9. Publication and notices to
property owners in the district will go out at least 10 days before second
meeting (Public Comments).
10. Once bids are
approved, the second Township Board meeting will occur.
11. The Assessing
Department will prepare the S.A.D. Roll.
12. Publication
and notices to property owners in the district will go at least 10 days before
third meeting (Hearing on Roll).
13. A third
meeting will be held by the Township Board to approve the Special Assessment
Roll.
If we can be of any further
assistance, do not hesitate to call (248)960-7077.